Inmos Microprocessor Factory
The concept for INMOS is large, column-free flexible and universally serviced open operational spaces with a central circulation spine and central meeting space at its heart.
The fast-track nature of the project required the design to be responsive to any site and capable of being built in a range of sizes. The factory is located at Newport, Gwent, close to major transport routes. The 8,900 m2 building provides office and ancillary space, plus facilities for microchip wafer production.
Speed of design and construction were critical factors. The single-storey steel structure was conceived as a kit of parts, with maximum off-site prefabrication allowing the building to be erected bay by bay. The structure is a tubular steel assisted span-tension structure, supported by tension tie rods from the spine towers. This system provides uninterrupted column-free spaces for maximum internal flexibility. The roof is fabricated from 6m span steel decking with thermal insulation and a five-layer roof membrane. The external walls are based on a system of standardised mullions incorporating various infills: single glazing, double glazing, translucent or opaque panels. Wall performances and finishes can be varied as required. The initial design includes double glazing for office areas and solid insulated sandwich panels for production areas.
The building features a central circulation/service spine with internal wings for specialised activities. The spine is 7.2 m wide and 106 m long and acts as an internal street, wide enough for vending machines, public telephones, seating, meeting places, planted areas and waiting areas. Services from the plant room – hot and cold water, chilled water, compressed air, etc – run at high level in this main spine. The building is extendable along the spine in 13 x 36m bays. Offices and restaurants are on the south side of the spine and the clean room production area to the north. Production wastes are collected in linear floor trenches and supply services are distributed on service walls. A large clean room facility and shipping and receiving bays occupy the north side of the spine. The south side has one bay omitted, providing a landscaped courtyard between the offices and the restaurant. Assembly labs and main piped services plant room occupy three western bays of the south face.
Project information:
- Place: Newport, Wales
- Date: 1982 - 1987
- Client: Inmos Ltd
- Area: 8,900 m²
- Architect: Richard Rogers Partnership
- Structural Engineer: Anthony Hunt Associates
- Services Engineer: YRM Engineers
- Quantity Surveyor: GA Hanscomb Partnership
- Main Contractor: Laing Management Contracting Ltd
Awards:
- The Structural Steel Design Award, 1982
- Eurostructpress Award, 1983
- Financial Times Architecture at Work Award Commendation, 1983
- Constructa-Preis for Overall Excellence in the Field of Architecture, 1986
--Rogers Stirk Harbour + Partners 14:09, 12 March 2015 (UTC)
Featured articles and news
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.